P 6 to MSP 2007

Rohit KMember for 18 years 5 months
Created
2
3
0

Dear All,

I have imported a project from P6 to MSP 2007. The import was successful. But I have noticed that the Summary tasks shows the durations in Days while the subtasks / activities are in Hours. Also the predessor linkages are the(activity numbers + period in hours).

How to change the time period from hours to days?

Rohit

2 replies

Oldest first
  1. 0
    Paul Harris ·

    You have to overtype the

    You have to overtype the durations with the day value.

    Ther is an article on my web site under technical articles about importing Microsft Project files into P6 that may inteterest you:

    http://www.eh.com.au/technical_papers.html

    Paul E Harris

    Eastwood Harris Pty Ltd, Melbourne, Australia

    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training

    www.eh.com.au

    www.eastwoodharris.com

    www.primavera.com.au- a Primavera scheduling software resources site

  2. 0
    Rohit K ·

    Dear Paul H, Thank you, is

    Dear Paul H,

    Thank you, is there no other solution. I am looking for importing files from P6 to MSP.

    Rohit

Log in or join to reply