Total slack

Deepak GowdaMember for 15 years 4 months
Created
3
2
0

Good evening guys,

I have got one question i have scheduled one project in picrosoft project.

start date is : 18.07.2011

End date is 30.08.2011

Relation :FS

i have entered status date as 28.07.2011 and i dint updated any tasks, then i enetred F9 to caleculate mannually , i am not able to see any negative slack of 10 days (or delay of 10 days since i dint started any work) 

if any one has answer please let me know. thanks in advance please note i have tried with must finish contraint too but the resilt is zero

 

 

3 replies

Oldest first
  1. 0
    Deepak Gowda ·

    sorry its microsoft project

    sorry its microsoft project cheeeeeeers

  2. 0
    Rafael Davila ·

    Make sure you set a must

    Make sure you set a must finish project date constraint if you want to compute float relative to such date. It can create negative float or even a longest path with positive float.

    If you do not set a finish date constraint no negative float will be computed and float will be zero along longest path.

  3. 0
    Deepak Gowda ·

    Spot on!!!!!!!!!!!!! Thank

    Spot on!!!!!!!!!!!!! Thank you Rafael

     

    Cheeeeeeeeeers