Total slack
In the Open Standard
Deepak GowdaMember for 15 years 4 months
- Created
- 3
- 2
0
Good evening guys,
I have got one question i have scheduled one project in picrosoft project.
start date is : 18.07.2011
End date is 30.08.2011
Relation :FS
i have entered status date as 28.07.2011 and i dint updated any tasks, then i enetred F9 to caleculate mannually , i am not able to see any negative slack of 10 days (or delay of 10 days since i dint started any work)
if any one has answer please let me know. thanks in advance please note i have tried with must finish contraint too but the resilt is zero