Planning activities in "Hours" with MSP
In the Open Standard
Abdullah MerchantMember for 15 years 10 months
- Created
- 3
- 4
0
Greetings,
I was using P6 on my previous Project. I have a a 4 day shutdown plan to develope and I need to plan the start and finish in hours for the same.
I just cant find aany option with MSP 2007, like Primavera P6 where i can enter the planned start or the actual start in hours along with the date.
I will be working on a 12 hours per day calendar during the 4 day shutdown and i need to plan the activities in hours. and then update the actuals in hours too.
Please advise.
Thanking You,
Abdullah.