MSP 2007 Formulae
- Created
- 1
- 1
Hi,
Request your help in this querry of mine.Following is my querry and request
to revert back
I have uplaoded my schedule. It is resource loaded and non resource loaded
and has various formulae in the columns, I have tried. Please correct my
mistakes in using the formulaes,as some are giving the results and some are
not.
Thanks in advance to your replies and time spent on it.
Rohit
http://www.scribd.com/doc/61674568/Non-Resource-Loaded-Schedule?secret_password=2fgu9f28aktkgnmz26vn
&
http://www.scribd.com/doc/61675005/Resource-Loaded-Schedule?secret_password=1azdbjpsl0i8hs3o823y
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?