P 2007 - Visual Reports
In the Open Standard
Rohit KMember for 18 years 5 months
- Created
- 1
- 3
0
Hi,
This is with regards to the visual reports in MSP 2007. I wanted to know what are the things required to be included in the reports to prepare a simple report to be presented to the management for the following reports available in msp 2007,
BASELINE COST
BASELINE WORK
BUDGET COST
BUDGET WORK
CASH FLOW
EV OVER TIME REPORT
RESOURCE COST SUMMARY
RESOURCE REMAINING WORK
RESOURCE WORK AVAILABILITY
RESOURCE WORK SUMMARY
It is project professional 2007, standalone installation.
Thanks in advance.
Rohit
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?