Skip to content

MSP 2007 Sub-Tasks Moving

Tony McClennonMember for 23 years 10 months
Created
2
3
0

Hi,

 

Can't see if this has been asked/answered before - if so, apologies.

A colleague has produced a detail schedule in MSP, and when saved it was fine with all sub-tasks showing under the correct summary task.

However, when it is reopened, all the sub-tasks appear to be distributed randomly around the schedule, additional blank lines appear, and other tasks are renumbered.

We have looked at saving with and without sorting on, there are no groupings set up, and we are only using the Gant Chart view.

Has anyone else come across this problem before, and if so, was there a solution.

 

Many thanks.

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Tony You may have a virus

    Hi Tony

    You may have a virus or a corrupted file

    Best regards

    Mike Testro

  2. 0
    Tony McClennon ·

    Mike, Thanks for confirming

    Mike,

    Thanks for confirming our suspicions. We managed to establish which copy was the latest "non-corrupted" version and fortunately this didn't require much work to replicate that in the corrupted file. Annoying though!!!

     

    Thanks.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?