Tracking using % complete
- Created
- 6
- 5
Hi all,
Can a schedule from 15.02.11 to 14.08.12, duration of 547 days tracked as on 15.01.12, have a finish variance of 1389 days?
The above instance is for a schedule of my project. The schedule is tracked based on % complete. I am manually entering the % complete as on the status date. For me to report % complete is the percentage of quantity of that task being completed as on the status date.
Earlier the same schedule tracked a fortnight ago had a finish variance of 153 days as on 31.12.11.
Also on saving as a Baseline and then inputting the values why does the start / finish varies from baseline start / finish dates?
Rohit
6 replies
Oldest firstLog in or join to reply