Moving Tasks from one Summary to another
- Created
- 1
- 6
Hello,
I have a requirement to move some completed tasks from the existing summary task to another new summary task. I am able to do copy-paste. But baseline hours at the new summary task does not show the correct hours. At the new summary task, I would like to get sum of baseline hours for all the individual tasks under it. If I set baseline, it shows incorrect values. Please help me in doing this.
eg: there are 5 tasks under Summary Task - Old and baseline hours is 100. Suppose I have moved 2 tasks having combined baseline hours 30 to "Summary Task - New". As per my requirement, Summary Task - Old should show baseline hours as 70 and Summary Task - New as 30.
Thanks and Regards,
Rajesh
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?