MSP 2007 setting the reporting periods

Richard MilsomMember for 14 years 7 months
Created
1
3
0

Howdy... first post. dont shoot me if its a simple answer.

currently running the cashflow report in the visual report sections. our reporting period runs from the 20th to the 20th . how do i get the report to run 20-20 not 1-31?

so that our claim information matches our cost forecasts.

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Richard,in the Excel crosstab

    Richard,

    in the Excel crosstab chart setup, change the time unit to Days, then select the appropriate days; I cannot find any other way to do

    Alexandre

Log in or join to reply