Calculation Settings

Donna HernandezMember for 19 years 5 months
Created
5
4
0
I cannot find where to change the calculation settings in MS Project 2007. Can anyone help me? I need to make sure it is set for Retained Logic and cannot find where to verify.

Thanks

5 replies

Oldest first
  1. 0
    Darren Kosa ·
    Hi Donna,

    Sorry, I think Retained Logic is mostly used with the Primavera toolset and maybe one or two others. There isn’t a suitable equivalent in MS Project as it doesn’t use remaining duration to calculate EF or LF dates, only start dates and durations (and float of course).

    Can anybody else help?

    Regards

    Darren
  2. 0
    Donna Hernandez ·
    Does anyone know where I can find documentation on the calculation method used by microsoft?
  3. 0
    Rafael Davila ·
    Donna

    Under P3/SureTrak if an activity has been worked on (had progress) before one of its predecessors, choose how to display this out-of-sequence progress. When you choose Retained Logic, P3/SureTrak does not schedule the remaining duration of a progressed activity until all of its predecessors are complete. When you choose Progress Override, P3 ignores network logic and allows the activity to progress without delay. Neither option solves the issue of out-of-sequence; there are arguments in favor and against each method.

    Because you are looking for the option under MS Project I assume you know that.

    I believe you can set this under Tools/ Options/ Schedule, split in progress check box.

    Split in-progress tasks Allows rescheduling of remaining duration and work when a task slips or reports progress ahead of schedule. With this check box selected, if progress is reported on a successor task before the predecessor task is completed, the remaining work on the successor task can be shown as a split, using the same task dependency with the predecessor on remaining work. If this check box is cleared, remaining work is not split. The progress information is recorded on the originally scheduled dates, regardless of when the actuals took place. Likewise, remaining work is not rescheduled to maintain the task relationship. By default, this check box is selected.

    A matter of semantics.

    The major problem I had with MS Project with this regard is the lack of a report that identifies the existence of out-of-sequence and where. I tried to get a VB script to this purposes and never got it. For your knowledge there are some add-on packages that provide these reports but at extra cost.

    These reports are usually a listing of your out-of-sequence activities (tasks in MS Project language) their predecessors and type of relationship. These reports are essential as out-of-sequence might invalidate your update unless you solve the issue through changed logic. Out-of-sequence at times drives crazy some reviewers who do not understand the issue. Out-of-logic is common, is not a sin, and per-se alone does not mean bad planning but a change in course.

    Best regards,
    Rafael

  4. 0
    Donna Hernandez ·
    Thank you Rafael. This was well stated. I fully agree with your assessment of out-of-sequence logic and the argument of retained logic v progress override.

    I am working with a client who would like to stipulate in their contract that specific calculation rules be used when submitting schedules. They are specifying retained logic, Durations contiguous (not interruptible) and Float calculated on Finish Dates.

    I am having difficulty providing documentation on these calculation methods.

    Any thoughts?

    Regards,
    Donna
  5. 0
    Rafael Davila ·

    Handling out-of-sequence

    Retained Logic vs. Progress Override

    Retained logic and Contiguous Durations are mutually exclusive per software settings, unless you make the exception for in-progress tasks.

    It is your choice.

    Best Regards,
    Rafael