Add calender to custom fieldes

Dan MårtenssonMember for 16 years 8 months
Created
1
2
0

Hello planners,

 

I need help to add project calender to this formula.

 

([Start]+[Duration3]/480)

 

I have made a PERT add in to MSP 2010 and whant to display the optimistic ending in the summary.

I'm sure that someone is sitting on this knowledge on the forum.

Looking forward to seeing the solution to this problem.

 

Kind regards

 

Dan

 

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Dan,use the ProjDateAdd(

    Dan,

    use the ProjDateAdd( date; duration; calendar ) function

    Alexandre