MP automatically putting Constraints on activties

James BraghiniMember for 16 years 1 month
Created
1
5
0

Question: How can we stop MP from automatically giving an activity a constraint after updating baseline?

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    James,when you update the

    James,

    when you update the project with the option "Reschedule uncompleted work after the status date" (freely translated from French), MS Project assigns a Start No Earlier Than constraint to the unstarted activities, and a Resume Date to the activities which had started before the update and are suspended

    there is no way to refuse the constraint, or the activity will be scheduled back in the past

    Alexandre