Two Weeks Lookahead

Sizwe MsomiMember for 14 years 10 months
Created
1
4
0

Hi all

Please assist in creating a Two week Lookahead on MSP. Date range does not work properly.

 

Regards,

 

Sizwe 

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Sizwe,you could use the

    Sizwe,

    you could use the following:

    a. create 2 custom fields to store the status date and the status date + 2 weeks: Date1 = Date(); Date2 = ProjDateAdd(Now();4800;"Standard") (where 4800 is the number of minutes during 2 weeks according to the usual calendar, and "Standard" the name of the usual project calendar

    change these 2 parameters if needed

    b. create a task filter that reads: Start >= Date1 AND Start <= Date2

    Hope this helps,

    Alexandre