Skip to content

Cumulative baseline work

Bogdan DinuMember for 14 years 1 month
Created
1
2
0

Hi,

I am new at this forum and I hope that you guys can help me out.

I want to creata a column, custom field in MSP 2010 that contains baseline work cumulative from the start of the project all the way to the current status date. 

Can not find this funcation anywere, does it exist?

 

Kind regards

Bogdan D

1 reply

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hi Bogdan,Baseline Cumulative

    Hi Bogdan,

    Baseline Cumulative Work cannot be displayed in MS Project tables nor Resource Graph; you will have to export the data to MS Excel and create the table and the curve there

    It is also possible to use a Visual Report

    Alexandre

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?