% work Complete field
In the Open Standard
Nqabutho NcubeMember for 13 years 9 months
- Created
- 1
- 3
0
I am updating a project whos resource type is material, when I an updating the % work complete its not not rolling up to show the overal percentage work complete.
I have tried to change the resource type to work, how ever its giving me an overload on the resource before I can specify the maximun number of units and its pushing the project competion out by a couple of years.
How do I show the overall total number of physical work (hrs)
1 reply
Oldest firstLog in or join to reply