"Necking" Bars on Gantt Chart - MSP2007
- Created
- 2
- 5
Hi,
Apologies if this has been covered before.
I'm trying to show a task bar "necked" where there is no working time. In this case, I have a number of tasks that have a calendar that only allows work to take place between April and October, so I want to show the "non-working" period (i.e. November to March) on those tasks that cut across this period in a different format to emphasise the non-working time (hope that's clear!!).
I recall being able to do this with P3, but nothing springs to mind for MSP.
What I can't do is show the calendar in front of tasks, as this will cover all of the task bars, not just those allocated against the specific calendar.
Many thanks.
2 replies
Oldest firstLog in or join to reply