How INACTIVATE tasks affect Total Slack

Ernie BilbroughMember for 14 years 2 months
Created
2
4
0

In MSProject 2010 how do I have inactivate tasks to not be part of the total slack calculation.

2 replies

Oldest first
  1. 0
    Evgeny Z. ·

    Ernie,what do you mean

    Ernie,

    what do you mean exactly, can you clarify?

    Regards.

  2. 0
    Ernie Bilbrough ·

    Hi,I have tasks at the end of

    Hi,

    I have tasks at the end of my project that occur and finish 6 months out. I have made these tasks INACTIVATE. The active tasks that remain have a finish date this month (approx 6 months prior). Those active tasks have a total slack that evaluates the end dates of my INACTIVATE tasks. I don't want MSProject to use the dates of the INACTIVATE tasks.