Hello,
Need some help with a problem I have regarding work distribution in MS Project 2010.
Problem;
Task A
Duration: 5 days
Work: 30 hours
Start: 2013-03-04
Finish: 2013-03-08
Status date: 2013-03-05 (2days reporting)
This means that the resource should work 12 hours.
But, actual is 15 hours.
Here is the problem, MS Project places 3 hours on the next day after status date which is wrong (Future). I want Project to place the total hours before status date.
Is this possible?
Hoping for an answer
Thank you
Regards
Dan