Remaining costs spreadsheet
- Created
- 8
- 6
Dear guys,
I am trying to undestrand how the remaining costs work in Ms Project 2003. In Primavera P6 you are able to do this in several editors and it is easy to obtain spreadsheet data for budgted/actual/remaining where
Remaining = Budgeted - Actual
In the resource usage spreadsheet (only material cost items have been assigned in the planning) are available only data for actual (effective cost) and budgeted if a baseline has been saved. But nothing to get a distribution of remaining costs by the user defined timescale even if the Remaining cost column is displayable.
Somebody knows how get the remaining costs distribution?
Thanks in advance.