Remaining Duration & the Status Line
In the Open Standard
Phil PalmerMember for 23 years 5 months
- Created
- 7
- 4
0
Hi all, My client is using MSP 2003 and I am having difficulty showing the remaining duration of the activities to the right of the status line.
I have read through all the postings here on PP and understand that it cannot be done. The MSP ’Help’ says it can and I have checked all the relevant switched on Tools/Options/Calculations but the activities in progress still show the remaining duration to the left of the status line. Any assistance would be appreciated.
I have read through all the postings here on PP and understand that it cannot be done. The MSP ’Help’ says it can and I have checked all the relevant switched on Tools/Options/Calculations but the activities in progress still show the remaining duration to the left of the status line. Any assistance would be appreciated.
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?