Skip to content

what to do in MS Project

Mona SinghMember for 13 years 5 months
Created
3
6
0

 

HI All

I am well versed in MS project software. Basically I hell from training background to core industry. Currently I m working for a Underground Mining project. My job profile is SAP-PS & MSP.  Our project is basically managed by outsourced vender. My basic problem is that I never worked in any kind of project, so I request you to guide me, exactly what should I do in MS Project, so I can save my job. What kind of report a project needs ?

 

Thanking you in advance

 

Regards

Mona Singh  

3 replies

Oldest first
  1. 0
    Mohamed Bedjaoui ·

    Hi MonaIf your project is

    Hi Mona

    If your project is scheduled, the first think is to set the baseline.

    Ms project has standard report:

    • Overview
    • Current
    • Costs
    • Assignments
    • Workload

    Each of the above categories also contains several pre-designed reports. It depends on what is the need of stakeholder to control the project.

    Also it contains visual reports which utilises the of the tables within Excel or Visio, and these come in six categories:

    • Task usage
    • Resource usage
    • Assignment usage
    • TasksSummary
    • Resource summary
    • Assignment summary

    Regards

  2. 0
    Paul Harris ·

    I publish a number of books

    I publish a number of books on MSP, you may wish to consider buying one of these.

    Theyare available in paperback, spiral and eBook format.

    Regards
    Paul E Harris
    BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner
    Managing Director and President
    Eastwood Harris Pty Ltd, Australia
    www.eh.com.au,  www.eastwoodharris.com, www.primaskills.com.au  and www.primavera.com.au
    Project Control Consultants and Planning and scheduling software book and training material publishersRegards

  3. 0
    Henry Davis ·

    Mona,you can use the

    Mona,

    you can use the Microsoft Project software for basic planning of the different project tasks. You can schedule tasks, allocate them to resources, and if you have the cost of each resource, material etc., then you can track that also, and have a much better comparison of projectd timeline, costs versus actual costs, timelines.

    This is an excellent tool, but must be used and updated regularly. Do not use it only in the planning stage. It wiill really bear fruit if you use it during executing of the project, and can save you a lot of time and money, and provide much better control over the project.

    Hope this helps - Cheers - Davis.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?