As Late as Possible

Deepak JainMember for 20 years 9 months
Created
1
2
0

While using ALAP constraint, Could someone please suggest how to change the setting to conduct dates calculation from Free slack variable instead of Total slack ?

Thnx in advance,

Dipak

1 reply

Oldest first
  1. 0
    Gary Whitehead ·

    Dipak, I don't think you can,

    Dipak,

     

    I don't think you can, but if you discover otherwise please let me know. -This is one of my major gripes with MS Project.

     

    Good luck!

     

    Gary