Hi
I was wondering if anyone knew if there was a way to show the late start for activity that used the free float only; not the total float.
I know you can manually alter the dates to use the float but am wondering if there is an automated method too.
Thanks
Craig
I was wondering if anyone knew if there was a way to show the late start for activity that used the free float only; not the total float.
I know you can manually alter the dates to use the float but am wondering if there is an automated method too.
Thanks
Craig
14 replies
Oldest first- 0AFAlexandre Faulx-Briole ·OK,
I missed the point
the formula is (in French): ProjDateSub([Fin repoussée au plus tard le];[Marge libre];[Calendrier du projet]); should be in English:
ProjDateSub([Latest Finish Date];[Free Slack];[Project Calendar]), or something close
Hope this help this time
Alexandre - 0LLL.E.N. Lewis ·Starting with P2000 ...
Certain fields (Task: Cost1-10, Date1-10, Duration1-10, Finish1-10, Flag1-20, Number1-20, Start1-10, Text1-30; Resource: same as for Task) can have formulas.
Display the column, RightMouseButton on the column title and pick Customize fields from the popup menu.
To put in a formula, click on the Formula button.
There’s a number of Help topics associated with Formulas. Try a few things, if you have problems, report back with the formula that’s giving you issues. - 0JCJeremy Clarke ·I have a test set up where this seems to be working only partially:
A 1 day task showing 3 days Free Slack gives a start date 2 days after Early Start using the formula ProjDateAdd([Early Start];[Free Slack];[Project Calendar]). The same formula with Early Finish gives a finish date 3 days after Early Finish. Any ideas why this could be?
Another question: Does anyone know how to make the task itself move to the end of its Free Slack? (In other words the same action as the "As late as possible" constraint in Primavera)
Jerry Clarke - 0JCJeremy Clarke ·Hi Trevor
P3e does not have the zero float constraint that I remember from P3, only ALAP, which uses up the free float but not the total float. I suspect from my experience and your answer plus other inputs that this simply doesn’t exist in MSP. ALAP uses up the total float on an activity - as you say not v. useful!
By the way, do you or anyone else know if there is a term for the start and finish dates at the back end of free float (in the sense of early and late dates, where late dates are at the back end of total float)?
Jerry - 0TRTrevor Rabey ·Are you sure that P3 does not have zero free float constraint? I am sure it had it last time I looked.
Anyway, that is not relevant to this problem.
You could use a spare flag field to mark the Tasks you want to show at the late dates. Then make a new View (copy the Gantt Chart View). Then make a Bar Style which draws a bar from Late Start to Late Finish using "Task, Flag*" as the criteria. I would use a different colour so you can see the late flagged Tasks. This would just be a variation on the built in Detail Gantt View. - 0PHPaul Harris ·P3 does have a Zero Free Float but P3e does not.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers & Consulting
www.eh.com.au
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?