Dear Planners,

I have a schedule which I need to assign total cost of salaries (staff salaries), but the problem I am facing is that:

1- In January I have total amount $9000 salaries

2- In february I have total amount $ 9000 salaries

3- In March I have total amount $ 14000

4- In April I have total amount $ 16000

and the tasks which I need to assign cost resources are overlapped?

Best,

Moutaz

4 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Mountaz,not very easy with MS

    Mountaz,

    not very easy with MS Project; you could try as follows:

    1. create "pseudo"hammock tasks whose predecessors and successors are milestones with date constraints at the beginning and end of each month

    2. using the Cost field in the Task sheet, enter the monthly amount of salaries you mention

    Good luck,

    Alexandre

  2. 0
    Vaibhav Paydelwar ·

    Dear Mountaz, wht is pseudo

    Dear Mountaz, wht is pseudo hammock ?

  3. 0
    Alexandre Faulx-Briole ·

    Vaibhav,MS project does not

    Vaibhav,

    MS project does not know what a hammock task is; therefore, il you want to simulate a hammock task in MS Project, you have to copy and paste "paste special with a link" the start date of the predecessor milestone and the successor milestone with the "hammock"

  4. 0
    Moutaz Aldeib ·

    Alexandre,What is

    Alexandre,

    What is pseudo"hammock?

    Could you explain more?

    Best

Log in or join to reply