% complete at summary tasks

Kasun JayasingheMember for 12 years
Created
1
4
0

While tracking the project schedule i am finding problem. Some activities taking more duration then it was planned, so while updating the schedule i have entered actual start, remaining duration. Then the % completion is taking automaticallty. But the project summery task % completion is showing very much higher then it actually completed. How to solve this. Is there any other process to do the correct tracking. It will be very much help to me if anybody can answer me.

1 reply

Oldest first
  1. 0
    Paul Harris ·

    The % Complete is % Duration

    The % Complete is % Duration and will sunmmerise at Summary Levle based on the proportion of the total Actual Durations over the total of durations.

    The Physical % Does not summerise.

    This leaves % Work, so you would have to assign resources or you could do something with Custom Fields and formulae.

    Regards

     

    Paul E Harris
    BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner
    Managing Director and President
    Eastwood Harris Pty Ltd, Australia

    http://www.eh.com.au,  http://www.primavera.com.auand http://eastwoodharris.com.

    Project Control Consultants and Planning and scheduling software book and training material publishers

    Primavera P6 Version 8.3 eLearning available from http://www.primaskills.com.au/project-management-training/

     

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?