Hi Wayne,
It's not clear what assistance you might need. MSP has two built-in filters that would seem to fit the bill:
1. "Should Start By..." This filter shows all tasks with no Actual Start (AS="NA") and whose scheduled start is less than a date you are prompted for. (Remember AS is the limiting factor here. You can have an AS with 0% Complete, but you can't have >0% Complete with no AS.) You could easily copy and modify this filter specification to use the Status Date.
2. "Late Tasks" This filter shows all tasks with Status = "Late". According to support.office.com,
- If the timephased cumulative percent complete does not reach midnight on the day before the status date, then the Status field contains Late.
So this is a bit more expansive, actually looking at the %Complete value and judging if adequate progress is being made.
Personally I don't use either of these on a regular basis, so I can't vouch for their overall usefulness.