Creating Formulas in custom field to avoid #ERROR

Mefa PlannerMember for 10 years 3 months
Created
2
3
0

Hai,

I need help to create this formula in custom field ([ACWP]/[Cost])*100 to avoid #ERROR becoz some of data in cost is value 0..pls assist me

2 replies

Oldest first
  1. 0
    Tom Boyle ·

    Does this

    Does this work?

    IIf([Cost]>0,([ACWP]/[Cost])*100,0)

  2. 0
    Mefa Planner ·

    TQ so much Tom Boyle..its

    TQ so much Tom Boyle..its work nicely.