Microsoft Project and the As Late As Possible (ALAP) Constraint

Emily FosterMember for 15 years 2 months
Created
1
4
0

The default constraint in Microsoft Project is ASAP. This is the ideal for most forward scheduling situations. Here we look at the As Late As Possible (ALAP) Constraint http://ow.ly/XWd830aUwVd

1 reply

Oldest first
  1. 0
    Tom Boyle ·

    MSP ALAP's consumption of ALL

    MSP ALAP's consumption of ALL TOTAL SLACK makes it pretty useless for CPM-type forward scheduling in my view.  If you are scheduling just-in-time material delivery for an installation that has some slack (not the TS=0 case shown in the example), then the ALAP constraint will delay the installation.  This is probably not what you intend.

    MSP ALAP might be useful in a critical chain methodology, but those who are not explicitly managing feeding/project buffers should beware.

    Just an opinion.... 