Tasks to Milestones

Lyonel ScapinoMember for 9 years 4 months
Created
1
2
0

I have a task with a milestones at the end of it in an existing MS Project. The successor is linked to the milestones itself and has a lead time. It is a finish to finish link. But the lead time should still be on the predecessor task? or on the milestone itself? 

Given that it is a finish to finish relation it should be the milestone or the task that is considered as the predecessor?

Or should it always be the task that is the predecessor?

Isn t linking to a milestones going to cause trouble for future MS Project calculations and/or optimizations?

Many thanks

1 reply

Oldest first
  1. 0
    Tom Boyle ·

    lyonel,I am sorry that after

    lyonel,

    I am sorry that after reading your question 3 times, I still don't understand it.  Please re-phrase.

    Between any arbitrary task and an arbitrary milestone (i.e. a zero-duration task), Project allows one of four relationship types and any amount of positive or negative lag.  ("Lead" in this context means negative lag.)  Which to chose depends on the real-world restraints you are trying to model.  There is no arbitrary solution.  As a rule linking to and from milestones causes no problems in Project's calculations.

Log in or join to reply