MSP: Elapsed total float ignored - even when increasing threshold for critical tasks

Henrik IMember for 8 years 2 months
Created
3
4
0

Please see attached. What is going on here? Bug?

Many thanks 
Kind regards,
Henrik

3 replies

Oldest first
  1. 0
    Tom Boyle ·

    No bugs.Assuming you've left

    No bugs.

    1. Assuming you've left the project's "hours per day" at the default value of 8, then your critical slack threshold of 6 days is 6x8=48 hours.
    2. On the two tasks selected, the Total Slack is 2.63 elapsed days x 24 hours per elapsed day = 63.12 hours.
    3. Since 63.12 > 48, the two tasks are not Critical.
    4. For these tasks to show as Critical, you would need to increase the critical threshold from 6 days to 8 days (i.e. 64 hours).

    In this case, your true Critical Path might be difficult to discern without tracing the driving logic.

    Good luck, tom 

     

     

  2. 0
    Henrik I ·

    Many thanks Tom! Brilliant

    Many thanks Tom! Brilliant :-)
    I should have thought of that.

  3. 0
    Tom Boyle ·

    Henrik, glad you got it

    Henrik, glad you got it sorted.