Import actual data from Excel to MSP

Ilia BaranovMember for 16 years 4 months
Created
3
3
0

Dear planners

Is threre any correct way to import actual data from Excel to MSP сurrent schedule?   

Thanks!

3 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hello Iliapresuming the

    Hello Ilia

    presuming the actual data to be imported are stored in an Excel file with the MS Project Export/import format,

    open the file to be updated in MS Project,

    select the Excel file in the MS Project File, Open dialog,

    select the Update project option

    Alexandre

  2. 0
    Ilia Baranov ·

    Thanks Alexandre!  But i need

    Thanks Alexandre!  But i need a correct options for dialog bох? 

  3. 0
    Alexandre Faulx-Briole ·

    Ilia,"Merge the data into the

    Ilia,

    "Merge the data into the active project"

    Alexandre