MS Project 2016 - Is there a way of changing the relationship of a group of selected activities from FS to SS

Pranab Kumar DebMember for 19 years 8 months
Created
2
3
0

Hi, 

Is there a way of changing the logic of a group of task's from  FS to SS?

 

regards 

 

Pranab

2 replies

Oldest first
  1. 0
    Bogdan Leonte ·

    Show predecessor and succesor

    Show predecessor and succesor columns, copy paste in excel, delete the values from ms project, find and replace in excel FS with SS copy paste back in MS Project.
  2. 0
    Pranab Kumar Deb ·

    thanks Very much Bogdan

    thanks Very much Bogdan