Hi Team,
I am trying to create a cashflow dashboard in Power BI for the total cost from a set of PWA data.
I have Power BI attached to the database and have created the below DAX code having followed some youtube tutorials:
Cumulative total =
CALCULATE(
AssignmentTimephasedDataSet[AssignmentCost],
FILTER(
all(AssignmentTimephasedDataSet[TimeByDay],)
AssignmentTimephasedDataSet[TimeByDay] < max(AssignmentTimephasedDataSet[TimeByDay])
))
Where AssignmentCost is the cost field, I have used this for a monthly cost and it works.
Am i looking at this in the right way, help please nearly lost a whole day on this.
I have also tried to add a column to the dataset to do the running total using the code below and trying to point it at a specific project:
Rolling total cost = var CurrentDate = AssignmentTimephasedDataSet[TimeByDay]
var FilteredTable = FILTER(AssignmentTimephasedDataSet,AssignmentTimephasedDataSet[TimeByDay]<=CurrentDate)
&& Projects[ProjectName]= "Nimbin Water Main Resintatement"
return
Calculate(AssignmentTimephasedDataSet[AssignmentCost],FilteredTable)
Again no joy please help
Thanks
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?