Resource Allocation issue
In the Open Standard
Kevin John McGovernMember for 19 years 3 months
- Created
- 12
- 4
0
Hi, I am using V23.12.
I have a fairly small schedule which is fully resource loaded. All dates etc. are correct folowing update.
However, on one activiy in particular, the resource loading has been spread way beond the activity completion date.
Activity completion date is 23 Sept and the resource loading goes on into November. Curve is linear and late dates are only 2 days beyond finish dates.
Anybody any ideas how to correct this?
Thanks