Skip to content

Resource Allocation issue

Kevin John McGovernMember for 19 years 3 months
Created
12
4
0

Hi, I am using V23.12.

I have a fairly small schedule which is fully resource loaded. All dates etc. are correct folowing update.

However, on one activiy in particular, the resource loading has been spread way beond the activity completion date.

Activity completion date is 23 Sept and the resource loading goes on into November. Curve is linear and late dates are only 2 days beyond finish dates.

Anybody any ideas how to correct this?

Thanks

12 replies

Oldest first
  1. 0
    Kevin John McGovern ·

    Further udate on the above.My

    Further udate on the above.

    My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the resource goin on until September.

    This has me completely stumped 

  2. 0
    Kevin John McGovern ·

    Further udate on the above.My

    Further udate on the above.

    My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the resource goin on until September.

    This has me completely stumped 

  3. 0
    Kevin John McGovern ·

    Further udate on the above.My

    Further udate on the above.

    My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the planned resource going on until September.

    This has me completely stumped 

  4. 0
    Kevin John McGovern ·

    Further udate on the above.My

    Further udate on the above.

    My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the planned resource going on until September.

    This has me completely stumped 

  5. 0
    Kevin John McGovern ·

    Further udate on the above.My

    Further udate on the above.

    My data date is 04 Aug and I have activities already completed in July. However, the resource Assignments spreadsheet shows the planned resource going on until September.

    This has me completely stumped 

  6. 0
    Alex Lyaschenko ·

    If it is ok for you. I can

    If it is ok for you. I can run your schedule via external schedule analysis tool to identify the problem. 
     

    Alex Lyaschenko

  7. 0
    Kevin John McGovern ·

    Apologies for all the

    Apologies for all the duplicate messages. No idea how that happened.

    Anyway, issu is now solved :)

  8. 0
    Kevin John McGovern ·

    Apologies for all the

    Apologies for all the duplicate messages. No idea how that happened.

    Anyway, issu is now solved :)

  9. 0
    Kevin John McGovern ·

    Apologies for all the

    Apologies for all the duplicate messages. No idea how that happened.

    Anyway, issu is now solved :)

  10. 0
    Hamza BENOUFIR ·

    If it's okay for you, can you

    If it's okay for you, can you share with us the cause of the issue?

  11. 0
    Hamza BENOUFIR ·

    If it's okay for you, can you

    If it's okay for you, can you share with us the cause of the issue?

  12. 0
    Zoltan Palffy ·

    it should go until September

    it should go until September becasuse 23 Sept is you completion date

    are you looking at remaing early histogram ?

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?