Excel Import/Export Resource data problem P6
- Created
- 29
- 15
I do need some helping hands from you all on this basic problem.
The problem is when I exporting (Budget labor units,Resource name and ID) to excel then do some modification/amemndment on that column. After while importing back that excel file to P6 but i didn’t see any changes on my schedule. It’s still remain as previous.
I did this as what I did in P3 but it is still error.
I guess my P6 software have a problem
29 replies
Oldest first- 0APArnold Puy ·Hi Izam,
If you will export Resources assigned to your activities, try to use only the the Export Type "Resource Assignments" and include the "Budgeted Units" & Resource ID Name" in your column, just to avoid confusion. Some of the column title having the symbol of (*) cannot be modified in Excel.
Let me know if you did it otherwise, I can send you the steps.
Regards,
Arnold
- 0APArnold Puy ·Hi Izam,
First of all, thanks for appreciating my assistance. I am happy to help.
Regarding to your query, to assign resources using excel sheet:
1. Create first the resources in Primavera 6 Windows.
2. After creating, export to excel all the activities don’t have resources assign.
3. make sure that your export type is "Resource Assignment" and include the "Resource ID", Activity ID and Activity Name & Budgeted Units (If necessary).
4. In Resource ID (rsrc_id) column, assign only the unique Resource ID (This is the Resources you newly created in Primavera 6 Windows) to that particular Activity ID & Name and put the units under the “Budgeted Units” column.
Try this and let me know, otherwise I will send you the steps.
Regards,
Arnold
- 0KLKevin Li ·Arnold,
Sorry for getting back to you late. The problem is that when I choose to export both the activities & relationships. I added to export both ’predecessor name’ & the ’successor activity names’. When I open the excel file, I found that I got the first 4 letters of the activity name under these two columns. I did get the complete activity names at the ’activity name’ column. - 0ASAnkit Singh ·
Hello Everyone,I'm posting
Hello Everyone,
I'm posting this question here becuase I have'nt found found option for creating New Thread, Actually I have been suffering with one problem since two days I want to import CSV data into excel file and export it in sql file format, so I want to whether any option or efficient tool to solve this problem. Please resolve my problem as soon as possibleor give me any valuable suggestion to me.
Thanks in advance!
- 0ASAnkit Singh ·
Hello Everyone,I'm posting
Hello Everyone,
I'm posting this question here because I haven't found found option for creating New Thread, Actually I have been suffering with one problem since two days I want to import CSV data into excel file and export it in SQL file format, so I want to whether any option or efficient tool to solve this problem. Please resolve my problem as soon as possible or give me any valuable suggestion.
Thanks in advance!
- 0ASAnkit Singh ·
Hello Everyone, I'm posting
Hello Everyone,
I'm posting this question here because I haven't found found option for creating <strong>New Thread, </strong>Actually I have been suffering with one problem since two days I want to import CSV data into excel file and export it in SQL file format, so I want to whether any option or efficient tool to solve this problem. Please resolve my problem as soon as possible or give me any valuable suggestion. </p><p>Thanks in advance!</p> - 0GYGaurav Yadav ·
Hi Ankit Singh,There is an
Hi Ankit Singh,
There is an option in excel through which you could import csv file, to import csv file first of all open Microsoft Excel and go to Data option, here you will see an option where you can import data from external resource such as txt, xml, form web resources etc. But in case If you want to use any third party software to perform such kinds of action, you should be download MindStick DataConverter. This is very efficient tool through which you can perform many such type of actions and saved file in many extensions, basically it's free charge tool so you have not any difficulty to download it.
MindStick DataConverter Download Link: http://mindstick.com/Product/ProductDC.aspx
I hope it might be useful for you.
- 0MLMichael Lepage ·
Well, this might be a bit
Well, this might be a bit late, but for others who might be struggling with importing updates from excel, I've put together a step by step video tutorial with a real-world project example. If you're interested, have a look https://www.planacademy.com/excellerate-your-updates-how-to-import-your-subcontractors-primavera-updates-from-excel/
Also, on re-importing data, all excell data must be of "TEXT" type for the reimport to work. It's all outlined in the post.
Regards,
Michael
- 0ARAli Reza ·
Hi everybody, Please help me
Hi everybody,
Please help me to solve my problem.
I cannot export schedule from P6 to excel. The below error message is coming:
"Export failed. Unexpected error from external database driver (1) please contact your administrator to correct the problem."
Please advice me how to solve this problem.
- 0ARAli Reza ·
Hi everybody, Please help me
Hi everybody,
Please help me to solve my problem.
I cannot export schedule from P6 to excel. The below error message is coming:
"Export failed. Unexpected error from external database driver (1) please contact your administrator to correct the problem."
Please advice me how to solve this problem.
- 0SASteven Auld ·
Keith,As Zoltan stated
Keith,
As Zoltan stated earlier, there appears to be a bug in some of the Microsoft updates installed on the 10th October.
These contained updates to the Microsoft Jet Database Engine & it appears to be causing Database issues with Microsoft Access as well.
There appears to be a couple of Microsoft updates that may be causing the issue depending on Windows Version.
See link below for possible solutions:
Please note that this bug has been reported to Oracle (Last Update 6th November):
Steven
- 0VKVikas Kulkarni ·
Thanks for your reply Dear
Thanks for your reply Dear Mr. Izam Zakaria.
I am trying to import just all the "Resource Names" - I tried many times, but in vain.
I tried searching for YouTube Videos where only "Resource Names" are imported - But could not find a single such video.
I added 2 resources manually in Primavera i.e. NLD-21 & NLD-22 with all details & then exported to Excel with the following fields - Using the Resource Export -
rsrc_short_name rsrc_name rsrc_type unit_id role_id def_qty_per_hr max_qty_per_hr Resource ID Resource Name (*)Resource Type Unit of Measure (*)Role ID Default Units / Time(h/d) (*)Max Units/Time(h/d) rsrc_short_name rsrc_name rsrc_type unit_id role_id def_qty_per_hr max_qty_per_hr Resource ID Resource Name (*)Resource Type Unit of Measure (*)Role ID Default Units / Time(h/d) (*)Max Units/Time(h/d) NLD-21 Parthiban Labor 8 12 NLD-22 Vijay Labor 8 12 NLD-23 VIKAS Labor 8 12 NLD-24 ANIL Labor 8 12 NLD-25 Sumit Labor 8 12 Then I opened the Excel file and deleted all other resources which are not part of the current project and added 3 more resources i.e. NLD-23, NLD-24 & NLD-25 with details as specified above.
Then I imported this resource added Excel file in Primavera - But these newely added 3 resources do not get imported even though Primavera displays that the "Import was successful" - I tried atleast 15 different Permutations & Combinations of adding and deleting fields, etc, etc but its not working out. The newely added 3 resources are Not Imported.
Can you tell me why? And what to do?
With Thanks & Best Regards