Actual Units vs Actual Regular Units?

Hamza BENOUFIRMember for 6 years 8 months
Created
1
3
0

Hello,

What is the difference between Actual Units vs Actual Regular Units. This is the first time I stumble upon Actual Regular Units and I'm unsure what it means. The hint feature isn't very helpful and neither does Google.

When I apply actual units on activity level, I usually just calculate earned units and apply them as cost and real actual hours/costs is managed separately from P6. Would the difference change between a case where the true actuals are applied in P6 and the case where only the earned are applied as actuals?

Thanks,

1 reply

Oldest first
  1. 0
    Renzo Constenla Bravo ·

    Hi:for the software

    Hi:

    for the software Primavera, actual regular units (for labor resource, as m-h) correspond to non-overtime worked. 

    Actual units include the overtime units.

    Useful to differentiate for costs purposes (it possible to limit the regular units and set a different price -factor- for overtime).

     

    regards