Comparison between Planned & Actual Progress
- Created
- 20
- 10
20 replies
Oldest first- 0AHAthar Hashmi ·i want to compare planned with actual. planned %age will be same as per the status date but actual %age can be more or less or equal depending upon the actual site progress. I want to show both progress, e.g planned is 50% and actual is 40% without changing any date. How can I do this?
- 0RMRodel Marasigan ·Athar,
You can use Activity Usage Spreadsheet and Select the following Fields:
1) Under Cumulative and Time Interval ->Earned Value Group:
->Cum Plan Value Cost or Unit
->Cum Earned Value Cost or Unit
->Plan Value Cost or Unit
->Earned Value Cost or Unit
Note: Earned Value is your Physical Progress (Actual)
2) Right click on Spreadsheet table and select Spreadsheet Option then Tick Calculate Average and enter the Budget Unit or Budget Cost over 100 and under unit of measure enter % then click apply or Okay.
Ex: Total budget cost = 10,000,000 /100 = 100,000
It should display the Plan Value and EV % cumulative and time interval. You can change the name to Plan% and Act% if you want.
Note: to match the Progress display on Activity Window Column you must have same cut-off date as timescale.
Ex: Timescale = Monthly = Datadate = July 30 2010 05:00PM
Timescale = Weekly should match on setting First day of the Week (i.e. Mon cut-off/datadate = Sun or Sat) - 0PTPinan T. ·hi athar
this was solved by Arnold Puy already in one of his posts in the forum:
"1. Let say you have 10 digits (e.g. 1234567890).
2. In this case, you can only have the 6 digits as a whole number but you can have as many numbers with decimals places (e.g. 123456.7890).
3. In order to convert the decimal into whole number, you need to delete the period/dot (.) using (<-) backspace or delete on your keyboard.
4. Just simply point your cursor in between the 6 & 7 numbers and delete the point/dot using the No. 3 step. The result 9e.g. from 123456.7890 to 1234567890)." - 0APAnbin Ponnith ·Hai Pinan T
1.Thanks For ur reply its Work where my Total budget cost 15800000
I gave divide interval by 1580000 & Its Works Fine.
In Another project I am having Total Budget cost of
343509538 .I am able to type as whole number
I want to Divide interval by 3435095.38(to show as 99.77%) its not working
I am able to add decimal only after 6 digit
Regards
Anbin
- 0RMRodel Marasigan ·Anbin,
The technique is to type the 6digit then decimal and add the rest of the number. Remove the decimal but if you required seven digits remove the others and it should work fine. Decimal is nothing if you have more than 6 digit whole number. You should get 100% equivalent. - 0ZTZhang Ting ·
Mr Rodel: I followed your
Mr Rodel:
I followed your instruction on your post #8, but after i entered unit of measure "%" ,the unit % of Plan Value and EV % can't display . Moreover how to change the magnitude of the value of Plan Value and EV % Ex: from "1" to "1.00%"
Best regards!
- 0ATAB Timo ·
Rodel,Thanks for the sharing
Rodel,
Thanks for the sharing information.one issue if you further clarify.
Activity spreadsheet window- --> right click ---> spreadsheet option ---->click "calculate average" --->here i have to enter 1853469.89 (cost is 185346989 Sr / 100 = 1853469.89) , but it is not taking complete value i,e not taking more than 5 digits number). can you check this option and solve the issue????
Regards,