Prioritization when leveling with P6
In the Open Standard
Jean DesjardinsMember for 3 years 7 months
- Created
- 3
- 3
0
Hello guys,
I am currently leveling resources in a oil refinery turnaround project.
I have about 40 heat exchangers that need to be disassembled, cleaned, inspected and reassembled.
The customer wants to reassemble every heat exchanger as soon as the inspection is completed.
However, P6 sometimes pushes the reassembly later than other exchangers activities having a lower priority level.
Did anybody experienced similar situation or any suggestion to resolve this issue?
Thanks in advance