Performance over VPN (P6 v23.12)
- Created
- 6
- 2
Hi all,
We've recently upgraded our P6 install to v23.12, and have one lingering snag that myself and our IT dept can't solve. I'm hoping someone else here may have had similar and managed to resolve!
While in office, performance is spot on - we can schedule projects fine, and importing of XERs is pretty quick.
While working at home via VPN - scheduling works, but is slow, and any XER imports of a moderate size end up timing out and throwing error codes (relating to the time out, we found). We've investigated via our installation consultants, RPC, and also hit a dead end. IT guys have tried all sorts, and last try was the below:
Oracle dont recommend any AV exceptions other than the standard SQL exceptions which are already in place.
I have however added a firewall rule allowing explicit access to the application ports for VPN users, as thats the only thing left open to try.
Any help would be much appreciated. As we have the EPPM version, we can import via web app at least, but not ideal!
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?