How do you handle multiple weather downtime periods within a single activity in Primavera P6?

George VellisMember for 8 months
Created
1
258
1

When tracking progress, we often need to account for downtime events such as bad weather. In MS Project, this is easy to tracki using the reschedule of uncompleted work, which allows an activity to be split multiple times based on actual events reported in DPRs(daily progress reports).

For example, a foundation activity may require 15 days of productive work but experience 5 days of weather downtime during execution. This allows us to clearly separate operational work from downtime while maintaining accurate progress tracking.

In Primavera P6, the Suspend/Resume feature appears to allow only a single interruption per activity. How do typically handle activities that are interrupted multiple times due to weather, permits, access restrictions, or other contingency events? What is considered best practice in P6 for this situation?

Please check the below attachement example

1 reply

Oldest first
  1. 0
    Ramesh ·

    P6 only gives you one Suspend/Resume per activity, so for repeated interruptions there are two common approaches. They serve different purposes, and I'd use both.

    1. A weather calendar with the actual downtime as exceptions (for day-to-day progress). Put weather-sensitive activities on their own calendar, and each time the DPR records a lost day, add that day to the calendar as non-work. The activity stretches across the lost days, remaining duration stays as productive days, and actual duration doesn't get inflated by downtime. In your example, the foundation shows 15 working days spread over 20 calendar days. Keep the calendar specific to the area or crew it applies to, not shared across the project.

    2. Split the activity around recorded delay activities (when it may become an EOT matter). Calendar exceptions are invisible when someone compares two updates: the dates move and nothing shows why. If the downtime could support a time claim, split the work into Part 1 and Part 2, and insert a "Weather downtime" activity in the logic between them, with actual dates from the DPRs. It's more work, but the interruption is visible and traceable.

    Either way, record the downtime days in the update narrative, and ideally in a UDF or notebook against the activity, so the DPRs and the schedule tell the same story.