Hi,

Can anybody help me on this? Im having a problem importing MS Project files(2007 format) in Primavera V7.0. Is there any workaround or fix on this thing?
MS Project 2007 also doesn’t allow to save as MPX format.

In Primaver, only MPX and XML are available in the Import formats.


Thanks in Advance.

26 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi RJ,

    You need to convert first your MPP to MPX otherwise, you cannot import.

    If you don’t have the Converter, follow the link below:

    http://www.projectstatus.com/pub/

    and look for MppToMpx.exe

    BDW, Sensya na kung hindi kita nasagot. Sobrang Busy. I will answer your query sooner or later.

    Regards,

    Arnold
  2. 0
    RJ Rivera ·
    Hi Arnold,

    Thanks for the reply, I got rhe problem fixed. I am running Windows Vista Ultimate, P6 v7.0 and microsoft Project 2007. I have a virtual box where windows XP is installed, what I did was I’ve installed MS Project 2003 on the virtual box. And guess what, when I got back to VIsta-P6 v7.0, the mpp selection in import feature is already available.

  3. 0
    Keyel Isorena ·

    Hi guys, am having problems as with RJ, though in my case am using windows xp and p6 sp2 and ms proj 2007. I have checked out the mpptompx file Arnold said but somehow its not working.. it does some process (i think) but no progress bar and the file i was trying to convert is still an mpp and it havent created mpx file at all. btw, i am  receiving this event code "CWRBC-1016-7" with this type "EOleSysError" and description "Call was rejected by callee"  with the following detail.

    *****************************************************
    * EXCEPTION REPORT *
    *****************************************************
    Date: 08-Oct-10

    Executable: PM.exe
    Application: Primavera Project Management
    Event Code: CWRBC-1016-7
    Message:
    Call was rejected by callee

    Context:
    1: TfrmWizImport.wizImportBeforeShowPage
    2: TfrmWizImport.RunImportWizard
    3: TfrmMain.actHomeExecute
    4: TfrmMain.actFileImportExecute
    5: TCFormManager.SetToolbar
    6: TfrmLogin.FormCreate
    7:
    8:
    9:
    10:

    Detail:
    Type: EOleSysError
    Object Type: TfrmWizard


    Components
    ==========
    ORI: ORI Win32 #
    ORI/DB: PMDB,0601.0011.0001.0001
    IMG: IMG Win32 #1000

    System Info
    ===========

    OS Version: Windows NT ver 5.1, build 2600, Service Pack 3 (Intel Pentium)

     

    I am not sure if RJ is receiving this error as well.

     

    Hope you guys or some other members has a solution to this kind of problem.

     

    Regards,

    Keyel

  4. 0
    Alexandre Faulx-Briole ·

    Hi guys,

    MS Project 2007 and 2010 simply are not compatible with Primavera PM6, whatever Windows OS you are using; that's why the MPP file format is available when you do have MSP 2003 installed instead of MSP 2007 or 2010.

    You may export MSP projects as XML files and import these XML files into Primavera PM6.

    Alexandre

  5. 0
    Ivan Botha ·

    MSP xml - no progress

    Hi Alexandre

    Maybe you can help me The Client want a program in MSP so I because I do not have MSP on my machine I export it from P6.7 as an XML file and open this XML file in MSP. However we noticed that the progress (actual start / finish and remaining durations) do not show. Is there something we do wrong? Is there a setting in MSP required.

    Your help will be appricated as I have place this question in the forum about two weeks ago and to date had no replies.

    Thanking you in advance

    Ivan

     

     

  6. 0
    Alex Krenvalk ·

    For restoration ms project

    For restoration ms project files there is a microsoft project recovery. The program is able to start under any Windows OS. The utility can show the results of recovery as a table. It doesn't change source project data during repair.

  7. 0
    Mateo Sanin ·

    Hi Keyel, This is really

     

    Hi Keyel,

     

    This is really late but it might do some good to to other people having the same problem.

    I was getting the same error code and at the same time Microsoft Project was opening for some unknown reason.

    What was happening was that I had the decimal delimiter set to "," which causes some kind of conflic with MSP, when I changed it to "." I no longer got the error message and was able to export freely.

     

    In order to change the delimiter go to Control Panel->regional settings

     

    hope this helps

  8. 0
    Sterling Gallagher ·

    Hi all A big thanks to Arnold

    Hi all

    A big thanks to Arnold that file converter worked perfectly.  I had tried a couple of other converters previously with no success so you have just solved a huge problem for me.

     

    Regards

    Sterling

  9. 0
    Brave G ·

    Arnold, Thanks for your

    Arnold,

     

    Thanks for your convertion. the problem i am having is after converting to Mpx using your link and moving onto the process of importing to MSP. I get these two error codes (IEECF-3519-9  PRMDB-0423-C ).  when i check P6 V7 which is wat i use i find the project with the WBS with no activities.

     

     

    Any suggestions

  10. 0
    Brave G ·

    Arnold, Thanks for your

    Arnold,

     

    Thanks for your convertion link. the problem i am having is after converting to Mpx using your link and moving onto the process of importing to MSP. I get these two error codes (IEECF-3519-9  PRMDB-0423-C ).  when i check P6 V7 which is wat i use i find the project with the WBS with no activities.

     

     

    Any suggestions

  11. 0
    Brave G ·

    Arnold, Thanks for your

    Arnold,

     

    Thanks for your conversion link. the problem i am having is after converting to Mpx using your link and moving onto the process of importing to MSP. I get these two error codes (IEECF-3519-9  PRMDB-0423-C ).  when i check P6 V7 which is wat i use i find the project with the WBS with no activities.

     

     

    Any suggestions

  12. 0
    Sudheer Kumar Panchadar ·

    Hi I am trying to import

    Hi

     

    I am trying to import MSProject file 2010 version (.MPP) to P6 version 8.2

     

    But there is no opton in P6 to convert .MPP file.

     

    Is there any latest toll that converts MPP file cretae in MSProject 2010 version to P6 ver 8.2

     

    Thanks in advance.

    If you have can you psl email to me at skpanchadar@hotmail.com

  13. 0
    Brave G ·

    THe guaranteed way to import

    THe guaranteed way to import from any microsoft forget all other convertion link bullshit.

     

    First import msp into excel......

    second import msp into primavera whatever version

    the import to primavera will usually not come out nice from the second step. so export from primavera back to excel then import back to primavera. you shd be fine.

    last when you have done this. u need to create a new eps and import wbs only into these new eps.  then finally import the first excel import from msp into this and sort under appropriate wbs..........

     try this...

     

     

    Goodluck.....

  14. 0
    Arash Arbabi ·

    I have the same issue, did

    I have the same issue, did you have any luck with it?

     

    I also had the MSP file converted to MPX and still doesn't work

     

     

    Thanks

    Arash

  15. 0
    Sagar Kadam ·

    Any one help me for

    Any one help me for conversion of mpp file to mxp file ?

    Please send me link and method of conversion.

    thank,

    SAGAR KADAM

  16. 0
    Sagar Kadam ·

    Any one help me for

    Any one help me for conversion of mpp file to mxp file ?

    Please send me link and method of conversion.

    thank,

    SAGAR KADAM

  17. 0
    Khuong Do ·

    I have upload the tool in

    I have upload the tool in this article.

    Kindly download here : https://doduykhuong.wordpress.com/2016/02/04/convert-microsoft-project-m...

  18. 0
    Zoltan Palffy ·

    there are several converters

    there are several converters one from primavera and one from Smatworks the one from smart works you convert from a MPP to a PPR then from a PPR to a MPX.

    here is the link for smart works

    http://smartworks-mpp-2-ppr-converter.software.informer.com

    here is the link to the Primavera converter

    https://www.dropbox.com/s/dc199eplqtnv059/MppToMpx.exe?dl=0

  19. 0
    Girish Bhave ·

    Hi Guys,Can i get MPP to MPX

    Hi Guys,

    Can i get MPP to MPX converter online for free. 

    Thanks & Regards,

    Girish Bhave

     

     

  20. 0
    Zoltan Palffy ·

    if you give me your email

    if you give me your email address I can send the Converter

  21. 0
    Vladimir Liberzon ·

    In mpx a lot of data will be

    In mpx a lot of data will be lost.

    I don't remember if MSP 2007 exports to xml.

  22. 0
    Zoltan Palffy ·

    try

    try this 

    https://www.dropbox.com/s/ui07q1npo84p8ha/MppToMpx.zip?dl=0

  23. 0
    Girish Bhave ·

    Hey Zoltan,My email ID is

    Hey Zoltan,

    My email ID is gbhave@gmail.com. YOu can send the convertor on to this email ID.

    Regards,

    Girish Bhave

     

  24. 0
    Zoltan Palffy ·

    Girish BhaveThe email that

    Girish Bhave

    The email that you provided has rejected my zipped file need a different email address

  25. 0
    Royce Zeigler ·

    Hello Fellow UsersI am having

    Hello Fellow Users

    I am having a similar Problem....I am trying to Export fro MS Project 2013 to Oracle Primavera P6 v. 7 ?

    Please Help as I have all my data in MS Project and the Company purchased v.7 P6.....

    My email is:     royce.zeiglersr@gmail.com

    phone is:        832-427-7538

     

    Thanks

    Royce Zeigler Sr. 

  26. 0
    Zoltan Palffy ·

    save msp project as a xml and

    save msp project as a xml and then in p6 import the xml