P3E - Backup of Databases

Forum GuestMember for 17 years 8 months
Created
3
5
0
I have recently had the pleasure of having to restore a P3E database and it did not go so well. I am currently using Arcserve with a SQL agent to back up my database. I am wondering if anyone has any experience with Backup software that works well with P3E. I have called and asked Primavera and they will not recommend any software for backup. If anyone could let me know their experience with this I would greatly appreciatte it.

3 replies

Oldest first
  1. 0
    Masoud Rahimian ·
    Dear Guest
    i have some experiances on ARCSERVE and SQL automatic backup and unfortunetly i didn’t underestand your problem.could you please describe what the real problem is.
    sincerely
    Masoud
  2. 0
    Henk van der Heide ·
    Isn’t it easier to make an export file (XER) om timely basis ??
  3. 0
    Rafael Davila ·
    Create a separate directory and using a simple utility like 2nd copy you can copy the database on a regular basis to this directory.
    Using the database wizard you will be able to open or connect to the saved database(S), to view the databases there is no need to restore the files using this approach.

Log in or join to reply