P3e Ver 3.5.1 Original Duraiton changing while upd
In the Open Standard
Afzal RazakMember for 22 years 7 months
- Created
- 5
- 1
0
Hi friends,
I joined today in this group and lemme begin by asking a simple problem which I encountered while updating my schedule.
My baseline plan shows Original duration of the whole project as 732 days, Project start date is 9th July 2002 and Project Finish Date is 08th November 2004 and 6 days, 8 hrs calendar(Friday is considered as holiday).
But when I started updating the scheudle, the original duration started changing(In the summary bar where the project name, Original Duration, Start & Finish is specified.
I would like to know why this is happening.
Regards
Afzal
I joined today in this group and lemme begin by asking a simple problem which I encountered while updating my schedule.
My baseline plan shows Original duration of the whole project as 732 days, Project start date is 9th July 2002 and Project Finish Date is 08th November 2004 and 6 days, 8 hrs calendar(Friday is considered as holiday).
But when I started updating the scheudle, the original duration started changing(In the summary bar where the project name, Original Duration, Start & Finish is specified.
I would like to know why this is happening.
Regards
Afzal
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?