How to revise budget unit without changing the current duration???

Ali RezaMember for 9 years 7 months
Created
13
4
0

Hi, 

I have a question, please help me. 

I revised durations in a schedule at P6 regardless of remaining units and remaining duration and submitted to HOD. 

The original budget available and duration type already defined by previous planner is fixed duration & units. 

The client asked to revise the budget and add the revised budget in P6 and then from P6 take the weekly planned budget. 

How can I revise the budget unit without changing the duration and date?

If I add the remaining units, the remaingin duration will change, so current completion date also will change. 

Please support me how to revise the budget units without affecting claimed completion dates and how to extract weekly budget unit from p6, same what we defined in excel in terms of weekly man-hour histogram????

13 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    change the duration type to

    change the duration type to fixed duration & units/time for all activities you can add that column duration type then do 1 then do a fill down 

  2. 0
    Zulham Julio ·

    excuse me sir, i,m newbie in

    excuse me sir, i,m newbie in this forum. how can i post a question in this forum? thank you

  3. 0
    Ali Reza ·

    Hi to every body, When %

    Hi to every body, 

    When % complete type is physical, how the remaing will be calculated by P6?

    Remaining duration I mean after changing of data date and  rescheduling???

  4. 0
    Zoltan Palffy ·

    got to tools Global change

    got to tools Global change and add a new global change

    where  physical percent complete is greater than 0

    then duration % complete  = physical % complete

    then execute the global change press change

    then committ chnages

    do this afret each update after inputting ALL physical % completes

    and before you calculate the schedule

     

     

  5. 0
    Ali Reza ·

    THANK YOU FOR YOUR ANSWERS. I

    THANK YOU FOR YOUR ANSWERS. 

    I HAVE ANOTHER QUESTION IN P6?

    I added I added remaining unit for an activity, after re-scheduling the start & finish date will change without respecting to predessor. When I remove the remaining unit, It follows the relationship. 

    Could you tell me how to avoid changing of dates in this situation?

  6. 0
    Ali Reza ·

    THANK YOU FOR YOUR ANSWERS. I

    THANK YOU FOR YOUR ANSWERS. 

    I HAVE ANOTHER QUESTION IN P6?

    I added I added remaining unit for an activity, after re-scheduling the start & finish date will change without respecting to predessor. When I remove the remaining unit, It follows the relationship. 

    Could you tell me how to avoid changing of dates in this situation?

  7. 0
    Zoltan Palffy ·

    change your duration tyeps to

    change your duration tyeps to fixed duration & units/time 

  8. 0
    Ali Reza ·

    Thank you very much. I got

    Thank you very much. 

    I got it. 

  9. 0
    Ali Reza ·

    Hi, How to make Duration %

    Hi, 

    How to make Duration % complete equal to physical % complete in P6?

    Then, whenever we enter physical % complete manually, the duration % complete also updated same. 

  10. 0
    Ali Reza ·

    Hi, Is any body can explain

    Hi, 

    Is any body can explain me about activity code and how to define new project activity codes? 

    I want to define activity codes to filter easily accordingly. 

  11. 0
    Zoltan Palffy ·

    filter for ALL activities add

    filter for ALL activities add a column look under the General Category and bring activity TYPE to the right

    on the first activity at the top in the activity type column change it to fixed duration and units/time

    now do a fill down in that column

    now go to the Projects directory

    make sure that your project is highlighted

    click the defaults tab and select fixed duration and units/time

    done

  12. 0
    Ali Reza ·

    Hi, It is requested to show

    Hi, 

    It is requested to show only procurement activities in P6 and all other ativities should be shown in summary level (wbs level). 

    I filtered but summary of other activities are shown without date and without gantt chart bar.

    Please help me in this case.  

  13. 0
    Zoltan Palffy ·

    just filter by wbs and on the

    just filter by wbs and on the left use the + and - to roll up and to unroll the procurment activities also in the gropuing select show grand totals