Hello,
I am not too easy at working with these notions in P3:
- let’s say we have a independent activity with one driving resource; to update this part of a project I will
a) enter the AS date for the activity,
b) update the resource actual to date again and again until the resource finishes its work,
c) not bother about the Pct value in the Activity form not going bigger and bigger with b),
d) enter the AF date for the activity when the resource has finished working
- now the activity is a Task: when I update the resource form, the activity is updated, whatever is the setup of Autocost
Am I right?
Thanks for your advices
I am not too easy at working with these notions in P3:
- let’s say we have a independent activity with one driving resource; to update this part of a project I will
a) enter the AS date for the activity,
b) update the resource actual to date again and again until the resource finishes its work,
c) not bother about the Pct value in the Activity form not going bigger and bigger with b),
d) enter the AF date for the activity when the resource has finished working
- now the activity is a Task: when I update the resource form, the activity is updated, whatever is the setup of Autocost
Am I right?
Thanks for your advices
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?