In the Open Standard
Lloyd YoungMember for 22 years 8 months
- Created
- 6
- 4
0
when scheduling in P3e/c it seems that i have to follow this process in order for all users to see updates.
1. F10 Commit Changes to database MUST be carried out on each individuals PC.
2. F9 Schedule can then be performed on any one PC. (Once the schedule is complete, all other users must be informed so the following can be carried out).
3. F5. After Schedule, to ensure that data on screen shows correct information everyone Should Refresh the data , this is achieved by pressing F5.(can be done at the same time by everyone)
The whole process can take upto 15mins,
Is this something that other users of P3e/c seen before?
1. F10 Commit Changes to database MUST be carried out on each individuals PC.
2. F9 Schedule can then be performed on any one PC. (Once the schedule is complete, all other users must be informed so the following can be carried out).
3. F5. After Schedule, to ensure that data on screen shows correct information everyone Should Refresh the data , this is achieved by pressing F5.(can be done at the same time by everyone)
The whole process can take upto 15mins,
Is this something that other users of P3e/c seen before?
6 replies
Oldest firstLog in or join to reply