Tricky scheduling of activity
- Created
- 14
- 4
I have a rather tricky situation. A certain activity must either finish before a certain date t0 or begin after the date t1, provided that t1 > t0. To illustrate the situation: If we cannot finish two-weeks activity before Christmass holidays (24th December), we will not even start it, and we will start the whole activity after the 5th of January.
Is it possible to implement this pattern in Primavera?
I thought about two possible solutions:
1. Assign two constraints :
Primary: Finish on or before 24 December and
Secondary: Start on or after 5 January.
Well, that doesn't work - even if I have a time to finish the activity before the 24 December, it is still postponed to 5th January. That means, that the Secondary constraint overrides the Primary.
2. Play with the Calendary
I can exclude the days from 24 December to 4 January from the Activity calendary, but that will simply "split" my Activity. The problem is that the Activity is indivisible - I cannot make a part of Activity before the 24 December and then continue the rest after the 5 January. I have to make the whole Activity either before, or the whole Activity after.
Is it possible to declare in some way or other the Activity to be a kind of Indivisible?
Thank you for your insights!
14 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?