P3e Baselines - Duration % Complete Changes ???
In the Open Standard
Forum GuestMember for 17 years 8 months
- Created
- 8
- 7
0
Hi all,
I have copied the original baseline of a schedule and applied actuals to this so it is shown ’on schedule’ this gives a duration percent complete of 8.45%
( we want to compare duration % complete on the baseline against the current plan duration % complete )
Can anyone tell me why in P3e when i attach the baseline, the duration percent complete on the baseline changes and matches identically to the current schedule and shows 4.5% although when it is detached it shows 8.45 % ????
Also, what is ’ Schedule Percent Complete ’
Regards
confused guest !
I have copied the original baseline of a schedule and applied actuals to this so it is shown ’on schedule’ this gives a duration percent complete of 8.45%
( we want to compare duration % complete on the baseline against the current plan duration % complete )
Can anyone tell me why in P3e when i attach the baseline, the duration percent complete on the baseline changes and matches identically to the current schedule and shows 4.5% although when it is detached it shows 8.45 % ????
Also, what is ’ Schedule Percent Complete ’
Regards
confused guest !
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?