Schedule Percent Complete will not ’roll up’
In the Open Standard
Forum GuestMember for 17 years 8 months
- Created
- 7
- 3
0
I have created a dummy schedule, created a baseline, then slipped the current schedule so the first 2 activities are past their baseline S & F dates, the Schedule percent complete shows 100% for both activities ( as this is saying they should of been completed w.r.t the baseline), but the percentages WILL NOT ROLL UP to Project level or whne group and sorted by grand total.......any ideas folks ?
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?