Planned Percentage

Arun VasanthMember for 17 years
Created
29
6
0
Dear friends
How can I view the planned percentage in P6.

With regards
Arun.V

29 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Arun,

    Go to View Menu --> Columns --> expand the Percent Completes and look for Schedule % Complete (Planned % Complete) then double click select OK.

    Regards,

    Arnold
  2. 0
    Arun Vasanth ·
    Thnxs Arnold
    Do we can use this for project planned percentage ..
    Before in P3 we were getting this information by scheduling report .At last last it will show like 35.5% som thhing like that .....
    We were taking the planned percentage from automatic scheduling ....

    Actual percentage from the schedule report of monthly updation manuallyyyy...

    I think Arnold nw u can solve my prob very easily in P6

    With regards
    Arun.V
  3. 0
    Arun Vasanth ·
    Dear Arnold

    Could u tell me how to find the Project Planned & Actual percentage over all????

    With regards
    Arun.V
  4. 0
    Arnold Puy ·
    Hi Arun,

    You can have your Planned % when you assign a baseline to your current project, and actual % depends on how you monitor your project. (e.g. based on quantity, cost, man-day, man-hour and etc.).

    Regards,

    Arnold
  5. 0
    Arun Vasanth ·
    No arnold
    Before in P3
    While we updating a percentage from the schedule log
    like 37.5 % completed some thing like ...

    Can we see the over all project progress percentage from P6 This is my question???

    Regards
    Arun
  6. 0
    Arnold Puy ·
    Hi Arun,

    You mean in Schedule Log? Unfortunately, there is no overall % complete shown in the schedule log.

    You can show the overall % complete in the column at Activities and WBS windows.

    Regards,

    Arnold

  7. 0
    Arun Vasanth ·
    Oh God
    Thn How we can calculatee the project progress percentage ???

    Regards
    Arun.V
  8. 0
    Arnold Puy ·
    Hi Arun,

    You can calculate your % complete using the three different types of "% complete type".

    1. Duration
    2. Physical
    3. Units

    Regards,

    Arnold
  9. 0
    Arun Vasanth ·
    Hai Arnold
    I not getting u ...

    For example
    U sheduled a program .After one month ur manager is asking that How much percentage of the project is completed ??

    How u will find in P6????

    With regards
    Arun.V
  10. 0
    Arnold Puy ·
    Hi Arun,

    What type of % complete that your Manager ask you? When you trying to present your % complete, it is based on what?

    1. Duration (Time)
    2. Units (Quantity or any resources you assign to your activities)
    3. Physical - User’s manually input or based on activity steps.

    Regards,

    Arnold
  11. 0
    Arun Vasanth ·
    In p3 --- Tools ----- Schedule----Schedule now --- view on screen----There we can see a report .In that report @ the end it is progress percentage ..
    Could I get that percentage in P6

    Regards
    Arun
  12. 0
    Arnold Puy ·
    Hi Arun,

    As I have mentioned in my previous post #7, you cannot find the % complete in schedule log of P6 as what you can see in P3.

    If you wish to check the log, go to Tools --> Schedule, select "View Log". Make sure you tick the "Log to file" and locate the SchedLog.txt

    Regards,

    Arnold


  13. 0
    Anbin Ponnith ·
    Dear Arun,

    Also how is your client expecting, Duration based % complete or cost based % complete.


    I guess you are aware how P3 calculates the Percentage complete displayed in the Schedule log.

    If you need the same %complete you can try it using global change.




    With Thanks & Regards,

    Anbin Ponnith
  14. 0
    Jay S ·
    % Complete = Actual / Forecast @ Complete.
    % earned = Budget (Original / Current x Physical % Complete)

    What is required.
  15. 0
    Wilfredo Jr. Flores ·
    hi Arun,

    Arnold is right. Actual Values (%) depends on how you will monitor the project. It may be based on cost, material, manpower. About the automatic scheduling, when you run the update progress in P6, it will automatically update all your resources depending on the schedule to get planned %, just like in P3, but it is a long process if you will need the planned % for each month. It is better to assign baseline, then get all planned % for each resources by report writer in P6 either monthly or weekly and fix it in excel. Then just add the actual percentage on every update.

    Hope this will help in your planning


    regards

    Wilfredo


    quoting
    "Thnxs Arnold
    Do we can use this for project planned percentage ..
    Before in P3 we were getting this information by scheduling report .At last last it will show like 35.5% som thhing like that .....
    We were taking the planned percentage from automatic scheduling ....

    Actual percentage from the schedule report of monthly updation manuallyyyy...

    I think Arnold nw u can solve my prob very easily in P6

    With regards
    Arun.V "
  16. 0
    Mustafa Ismayilzada ·
    Guys,

    Could you please let me know how to make % Shedule to be shown in Level 3 in P5?

    There is no problem to show the planned progress at activity level, but when you roll it up to let’s say level 3 it gets blank.

    Any ideas?

    Cheers
    Mustafa
  17. 0
    R. Catalan ·
    Arun,

    1) % Complete in P3 (also in Sched Log) = Duration % Complete in P6

    2) Autocost Rules "link/unlink remaining duration and schedule % complete in P3 = Physical % Complete in P6

    Mustafa,

    You have to cost-load your programme in order to roll-up the Schedule % Complete in P5.

    Best regards,

    R. Catalan
  18. 0
    Roldan Bartolome ·
    Arun,

    Send me your e-mail add and i’ll send you the percent completion type use in P6.


    regards,

    roldan
  19. 0
    Sitaram Sakamuri ·
    why are we unable to get the schedule % complete on the summary bars. Though the project is completed by 25%, the top summary bar is still showing 0 %complete while the activities are showing correctly. How to rectify it and is there a way to find the summarised % complete just like in P3. If not in P6, is there any way that can be done in excel (means to compute the planned % at various stages of the project). Do reply immediately
  20. 0
    David Kelly ·
    Schedule percent complete is based on money at the summary bar level. It will only display a value if:

    The activities have resources
    Those resources have a unit price.

    For those environments that do not use P6 for costing, set all the resources to the same price (e.g. $1.00) and then you will have a percent complete. that matches P3’s summarisation by resource. REmember Schedule % complete is from the baseline (we used to call it "planned percent complete")
  21. 0
    R. Catalan ·
    Sitaram,

    If your programme is not resource-loaded, you can still show the roll-up summary of Schedule % Complete by assigning expenses to your activities.

    And, with the assigned expenses you can do variance analysis by cost (Performance % Complete). But you still have to do tracking your programme by CPM (variance in days) to have the real picture of the current update.

    Best regards,

    R. Catalan
  22. 0
    Anujkumar Mishra ·
    Dear Roldan,
    Kindly send me percent completion type used in P6 at anuj.2121@gmail.com.

    Regards,
    Anuj
  23. 0
    Zq qz ·
    in the activity menu, click column , then find the percent you want in the list.

  24. 0
    Goli Rahmani ·

    Hi all How can i see percent

    Hi all How can i see percent complete plan and actual for wbs summary? Thanks
  25. 0
    Goli Rahmani ·

    Hi all How can i see percent

    Hi all How can i see percent complete plan and actual for wbs summary? Thanks
  26. 0
    Goli Rahmani ·

    Hi all How can i see percent

    Hi all How can i see percent complete plan and actual for wbs summary? Thanks
  27. 0
    Goli Rahmani ·

    Hi all How can i see percent

    Hi all How can i see percent complete plan and actual for wbs summary? Thanks
  28. 0
    Suru Kadam ·

    Guyzzz any one can tell me

    Guyzzz any one can tell me how do I find planned % from the baseline programme or from updated programme confused
  29. 0
    Zoltan Palffy ·

    planned what ? you need a

    planned what ? you need a measuring stick such as dollars or units

Log in or join to reply